ASX Announcement – 31 August 2026
Project Development and Infrastructure Works Update
Multiple de-risking workstreams at fully permitted Mt Ida Gold Project
Project Development
• Mining Lease granted for West Knell, where the Company recently
announced 9m @ 27.1 g/t Au1
, its best drill intercept to date
• Metallurgical test work to a feasibility study level of detail completed for the
+1.0Moz at 3.5 g/t2
Baldock gold deposit
o Metallurgical recovery averaged 91%3
• Mine geotechnical assessment to a feasibility study level of detail
completed for:
o Baldock open pits and underground
o Kestrel and West Knell open pits
Mineral Resource Estimate
• Updated Global Mt Ida Mineral Resource Estimate (MRE) underway
• Approximately 150km of drilling has been completed since the last MRE
update in February 2026
• Ballard’s entire drilling effort in CY2026 has been resource growth
• Baldock Maiden Ore Reserve will be based on the upcoming MRE update,
enabling the inclusion of an anticipated material increase in the MRE
supported by significant mineralisation reported during the year4
Infrastructure Works
• Exploration Camp expanded to 30 rooms
• Additional water production bores installed to support 2.5 GL/yr water
license
• Contract awarded to undertake the approved 4km Mt Ida public road
diversion
Corporate
• Ballard remains well funded with a cash balance of $62M at 30 June 2026
1
Refer to the ASX Announcement lodged by Ballard on 27 July 2026 for further information
2
Refer to the ASX Announcement released by Ballard on the 26 February 2026 for further information
3
Refer to the ASX Announcement lodged by Ballard on 7 April 2026 for further information
4
Refer to the ASX Announcements lodged by Ballard on 2 February 2026 and 22 June 2026 for further information
2
ASX: BM1
ballardmining.com.au
Ballard Managing Director Paul Brennan said:
“Our project development workstreams and early infrastructure works are progressing as
planned and demonstrate our confidence in the Mt Ida Gold Project.
Our near-term goals remain a 1.5 Moz MRE to underwrite an initial Feasibility Study with a
pathwayto a 2.0 Moz MRE. TheseMREmilestonesprovide areasonablebasisforan aspirational
target of an 8 Year and 10 Year Mine Life respectively”.
Ballard Mining (ASX:BM1) (“Ballard” or “the Company”) is pleased to provide an update on
Project Development and Early Works activities at the Mt Ida Gold Project (“Mt Ida” or “the
Project”).
Mt Ida is located 540km northeast of Perth in the Goldfields Region of Western Australia (Figure
1). The Project covers 26km of prospective Greenstone belt, folded around the Copperfield
Granite (Figure 2).
Ballard is pursuing a dual stream Resource Growth and Project Development strategy. The
Company’s focus for CY2026 is Resource Growth at the cornerstone +1 Moz at 3.5 g/t gold
Baldock Mineral Resource Estimate (MRE)5
and from satellite feed sources to support a
standalone operation at Mt Ida.
Figure 1 - Ballard’s Mt Ida Gold Project, located in Western Australia’s Goldfield Region.
5
Refer to the ASX Announcement released by Ballard on the 26 February 2026 for further information
3
ASX: BM1
ballardmining.com.au
Figure 2 – Mt Ida Project showing Baldock and satellite prospects gold resources (Feb 2026 MRE6
)
proximal to the regionally significant Copperfield Granite.
6
Refer to the ASX Announcement released by Ballard on the 26 February 2026 for further information
4
ASX: BM1
ballardmining.com.au
Project Development Update
Ballard’sdrillingprogram in CY2026hasbeen optimised towards near-termdevelopment rather
than fully testing the gold system potential at Mt Ida. Regional drilling has been largely
constrained to depths of ~150m which is suitable to define shallow open pit resources but not
designed to test for deeper, Baldock-style mineralisation. The satellites are being advanced to
supplement an initial production plan, with the testing of greater system potential to occur once
this is achieved.
Once Ballard has achieved an MRE which will support an initially targeted minimum 8 year Mine
Life, drilling activities will pivot to a combination of infill drilling to de-risk the first 8 years, and
growth drilling to support a 10 year plan. These production timelines are expected to be
achieved withMRE’s of 1.5 Moz and 2.0 Moz respectively,basedon atop-down goal of 100kozpa
production scale and a reasonable conversion of resource to reserve.
A high level project timeline is shown below (Figure 3).
Figure 3 – High level Project timeline
5
ASX: BM1
ballardmining.com.au
Infrastructure Works
Exploration Camp Expanded
An additional eight rooms have been installed at the existing exploration camp, expanding
capacity to 30 rooms (Figure 4). The additional rooms will be used by personnel undertaking
early works scopes and ultimately the contractor who will build the proposed accommodation
village to house the construction workforce (subject to FID).
Figure 4 - Mt Ida Exploration Camp and core processing area. Additional rooms installed are the two
blocks in middle of photograph (inset bottom right)
Additional Production Bores
Ballard has a total approved water abstraction licence of 3.7 GL/yr. The Lake Raeside
Paleochannel is located approximately 30km north of Mt Ida, and accounts for 2.5 GL/yr of the
total water license (Figure 5). The borefield location is connected to the Project siteby approved
Miscellaneous License L29/229 which allows for the construction of the borefield, pipeline and
access road.
Ballard has previously installed three production bores at Lake Raeside. As part of ongoing de-
risking for Project execution, the Company has now installed an additional four production
bores for a total of seven production bores. This will provide the necessary number of
production bores for a sustainable 2.5 GL/yr abstraction from the paleochannel.
A separate water license has been granted for 1.2 GL/yr from fractured rock aquifers around the
Baldock mining area for dewatering purposes. Ballard intends to install a number of dewatering
bores in the December Quarter.
6
ASX: BM1
ballardmining.com.au
Figure 5 – Installation of screen for water production bore at Lake Raeside Paleochannel. Inset showing
completed production bore and monitoring bore (inset top left), and ~30 L/s air lift testing of completed
production bore (inset bottom left)
7
ASX: BM1
ballardmining.com.au
Contract Awarded for Mt Ida Public Road diversion
The Company is undertaking a public road diversion ahead of a potential FID to safely integrate
the proposed mining and processing operations at Mt Ida into the local road network (Figure 6).
This will minimiseany interaction with publictrafficand allowconstruction activities to advance
unimpeded.
The road diversion contract has been awarded to diversified engineering, construction and
maintenance provider Archetype Contracting Group. The works are expected to commence
and be completed within the December Quarter.
Figure 6 – Baldock Mining and central Processing Area showing granted Mining Leases and approved
public road diversion
8
ASX: BM1
ballardmining.com.au
Project Background
The Mt Ida Gold Project hosts a JORC 2012-compliant Mineral Resource Estimate totalling 12.2
million tonnes at 3.0 g/t Au for 1.2 Moz7
of contained gold (Indicated and Inferred). The
cornerstone Baldock deposit, which hosts +1.0Moz at 3.5 g/t7
, forms the basis for initial
development opportunities at Mt Ida.
The Project includes seven granted Mining Leases and is fully permitted for mining, including an
approved Mining Proposal, Mine Closure Plan and Native Vegetation Clearing Permit.
Mining approvals are in place for both open pit and underground mining at the Baldock deposit.
A Works Approval for processing of up to 2.0 Mtpa and a Tailings Storage Facility has been
received, along with granted water abstraction licences for 3.7 GL/yr.
-END-
This release is authorised by the Board of Directors of Ballard Mining Limited.
Company contacts:
PAUL BRENNAN TIM MANNERS
Managing Director Executive Director
info@ballardmining.com.au
MICHAEL VAUGHAN
Fivemark Partners
michael.vaughan@fivemark.com.au
7
Refer to the ASX Announcement released by Ballard on the 26 February 2026 for further information
9
ASX: BM1
ballardmining.com.au
About Ballard Mining
Ballard Mining Limited (ASX: BM1) is an exploration and development company focused on advancing its Mt Ida asset
towards production. With current JORC compliant resources of 12.2Mt @ 3.0 g/t Au, a strong balance sheet and an
experienced team driving the project development, Ballard is pursuing a growth and development strategy.
The Mt Ida Project has high grade gold resources located on granted mining leases. The main Baldock area has
received full open cut and underground mining approvals with a Works Approval for up to 2.0 Mtpa Processing Plant
and Tailings Storage Facility. Ballard is rapidly advancing the Mt Ida Project through a dual stream plan to increase
confidence in the current MRE and increase the global resource inventory via an aggressive exploration program. All
modifying factors will be advanced simultaneously.
Competent Person's Statement
Information in this announcement that relates to exploration results is based upon work undertaken by Mr Todd
Hibberd, a Competent Person who is a Member of the Australasian Institute of mining and Metallurgy (AusIMM). Mr.
Hibberd has sufficient experience that is relevant to the style of mineralisation and type of deposit under
consideration and to the activity which he is undertaking to qualify as a ‘Competent Person’ as defined in the 2012
Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ (“JORC
Code”). Mr. Hibberd consents to the inclusion in this announcement of the matters based on his information in the
form and context in which it appears.
The information in this report which relates to Mineral Resources for the Baldock gold deposit at the Mt Ida Gold
Project have been previously prepared and disclosed by Ballard in accordance with the JORC Code. Refer ASX
Announcement released by Ballard on the 26 February 2026 for further information.
Past Exploration results and Mineral Resource Estimates reported in this announcement have been previously
prepared and disclosed by Ballard in accordance with the JORC Code in its Prospectus lodged with ASIC and dated
30 May 2025 (as amended by the Supplementary Prospectus lodged with ASIC and dated 17 June 2025) (the
Prospectus).
Disclaimer
This release may include forward-looking and aspirational statements. These statements are based on Ballard
management’s expectations and beliefs concerning future events as of the time of the release of this announcement.
Forward-looking and aspirational statements are necessarily subject to risks, uncertainties and other factors, some
of which are outside the control of Ballard, which could cause actual results to differ materially from such
statements. Ballard makes no undertaking to subsequently update or revise the forward looking or aspirational
statements made in this release to reflect events or circumstances after the date of this release, except as required
by applicable laws and the ASX Listing Rules.
10
ASX: BM1
ballardmining.com.au
Appendix A: Ballard Global Mineral Resource Estimate (February 2026)
Cutoff Deposit
Indicated Inferred Total
Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces
(000s) g/t Au (000s) (000s) g/t Au (000s) (000s) g/t Au (000s)
Open cut
0.5g/t Au
Baldock 2,916 3.9 362 395 2.6 33 3,311 3.7 395
Kestrel - - - 940 1.6 48 940 1.6 48
Golden Vale - - - 496 1.7 27 496 1.7 27
Bombay 711 1.3 30 711 1.3 30
West Knell 238 3.3 25 238 3.3 25
Jupiter 50 1.7 3 50 1.7 3
Tailings - - - 500 0.5 8 500 0.5 8
Underground
1.5g/t Au
Baldock 2,658 3.6 307 2,992 3.2 304 5,651 3.4 610
Kestrel - - - 80 1.8 5 80 1.8 5
Bombay 30 3 3 30 3 3
West Knell 192 2.4 15 192 2.4 15
Jupiter 90 2.7 8 90 2.7 8
All
Baldock 5,574 3.7 669 3,388 3.1 337 8,962 3.5 1,006
Kestrel - - 1,000 1.7 53 1,000 1.7 53
Golden Vale - - - 496 1.7 27 496 1.7 27
Bombay 740 1.4 33 740 1.4 33
West Knell 420 2.9 40 420 2.9 40
Jupiter 140 2.3 11 140 2.3 11
Tailings 500 0.5 8 500 0.5 8
Total 5,574 3.7 669 6,684 2.4 509 12,258 3.0 1,178
Notes:
• Open pit resources are reported within optimised pit shells based on A$4,500 per ounce gold price and
reported at 0.5 g/t Au cut-off grade.
• Underground resources are reported below optimised pits and constrained within mineralised domains in
optimised mineable shapes at 1.5g/t gold cut-off grade.
• All figures are rounded to reflect appropriate levels of confidence.
• Apparent differences may occur due to rounding.